Queens Garage – 12/06 – 12/10 – Weekly Construction Bulletin

The following is an anticipated work scheduled for 12/06/21 to 12/10/21.  

  • Excavation for community space foundations
  • Form and rebar for foundation walls & footings
  • Pour concrete for foundation walls, footings, piers, etc.
  • Backfill garage foundation
  • Rework existing sheeting & install final SOE for CS footprint
  • Install underground plumbing PA-PB
  • Underground electrical grounding and conduit

Please note that parking and sidewalk access restrictions on Union Tpke between 126th St and 132nd St are expected for the duration of the project. If you have any questions or concerns, please feel free to contact me via email or phone.